What is the Permit Process?

Rum River Construction Consultants reviews and processes building permit applications, performs on-site inspections of residential and commercial construction and ensures that all construction activity is in compliance with state and municipal building and fire codes.

Permits Requiring Plan Review

Permits that fall into this category include, but are not limited to, all commercial projects, new construction, remodeling,

additions, and decks.

Anchor 1

STEP 1

APPLICATION SUBMITTAL AND INTAKE REVIEW

Visit your jurisdiction page for application information.

Provide application and all supplements to your municipality or via Baseline Permits 

STEP 2

PLAN REVIEW

Rum River Staff reviews the application and supplemental information for compliance.

STEP 3

APPLICANT NOTIFICATION

Applicant is notified that plan review is complete & of any required fees.

Please visit the Jurisdiction page for payment options with your municipality.

Permit becomes active only after payment is made.

STEP 4

INSPECTIONS

All related documents are given to the applicant in person or via email detailing the required inspections.

It is the applicant's responsibility to contact RRC for the required inspection per the inspection record.

After each inspection, the applicant is sent an updated inspection record.

To schedule an inspection, email or call our office at

763-331-7722

or use the Scheduling Option on Baseline Permits.

STEP 5

PERMIT CLOSING

In order to maintain active status, inspections are required at intervals not to exceed

180 days.

Once all inspections are complete the permit is considered closed.  All documents are then  maintained by the jurisdiction.

Residential Set Fee Permits

Permits that fall into this category are primarily maintenance related, such as residential exteriors and mechanical systems.

Anchor 2

STEP 1

APPLICATION SUBMITTAL 

Visit your jurisdiction page for application forms.

STEP 2

INTAKE REVIEW

Rum River Staff, or your Municipal staff if applying in person, will review the set fee permit application information for compliance.

Please complete the online application via Baseline Permits or provide a .pdf copy, if not using Baseline online platform to

STEP 3

APPLICANT NOTIFICATION

Applicant is notified that review is complete & of any required fees.

If applying in person, you may be able to pay for the permit at that time.

Please visit the Jurisdiction page for payment options with your municipality.

Permit becomes active only after payment is made.

STEP 4

INSPECTIONS

All related documents are given to the applicant in person or via email detailing the required inspections.

It is the applicant's responsibility to contact RRCC for the required inspection per the inspection record.

After each inspection, the applicant is sent an updated inspection record.

To schedule an inspection, do so using Baseline Permits, via inspections email or call our office at

763-331-7722

STEP 5

PERMIT CLOSING

In order to maintain active status, inspections are required at intervals not to exceed

180 days.

Once all inspections are complete the permit is considered closed.  All documents are then  maintained by the jurisdiction.